August Community Update

We are excited to share that the building footings, storm drainage, and underground utilities are underway. In addition, we successfully passed a surprise DNR inspection for the stormwater drainage.

4-Week Look-ahead:

  • Completion of the east parking lots
  • Finishing the building foundations
  • Installation of temporary power to the trailer and building pad
  • Underground building electrical and plumbing work
  • Curb & asphalt installation in the parking lots is expected within the next 4-6 weeks
  • Seeding around the public road, planning for mid-September when the weather cools
  • The remaining sidewalk work is also anticipated to be finished in mid-September

We are pleased to report that we remain scheduled for completion in April 2026.

New Hospital Update

Exciting Progress on Our New Hospital!As we kick off 2026, we’re thrilled to share the incredible strides being made toward